Route 11 Reconstruction Project Update
The contractor working on Route 11 through Berwick plans to continue the reconstruction of a portion of Front Street through the business district next week.
On Monday, April 29, Barletta Materials and Construction, Inc. will switch lanes and begin excavating the right lane of Front Street from near Dunkin Donuts to Market Street, place sub-base material, and place two of the three new layers of blacktop. This phase is expected to be completed by Wednesday, May 8, weather permitting.
The third and final layer of blacktop will be placed after the Celebrate Berwick Festival, which is scheduled for Saturday, May 11.
Motorists are reminded that there will be no parking on either side of Front Street while this work is being completed but the sidewalks and businesses will remain open. One lane of traffic will be maintained throughout the work.
There will be several days where Mulberry Street will be closed while the excavation and paving work are completed.