Skip to content

Berwick Reconstruction Schedule

Berwick reconstruction narrative schedule As of April 3, 2013

Work Area:  Front Street from Dunkin Donuts to Market Street

April 1 to April 12

•Set up traffic control signing; mobilize equipment and saw cut to roadway in preparation for full depth reconstruction.

April 15 to April 24

•Excavate left side of roadway; place sub ase and pave to binder course.

• One lane of traffic will be maintained through the work area.

• There will be several days where Mulberry Street will be closed on the Subway side of Front Street for this work.

• No parking on either side Front Street from Dunkin Donuts to Market Street.

April 25 to May 6

•Excavate right side of roadway from the Mulberry intersection to Market Street. Reconstruction of the right side of the roadway from Dunkin Donuts to Mulberry Street was completed previously by the boroughs sewer project. This area will be milled and overlaid at the completion of the other work.

• One lane of traffic will be maintained through the work area.

• There will be several days where Mulberry Street will be closed on the Carpet store’s side of Front Street. Access to the municipal parking lot will be from the Market Street end.

• No parking on either side of Front Street from Dunkin Donuts to Market Street.

 

Work Area: Route 11 Southbound (Second Street) from Walnut Street to Market Street (includes a section of 11 NB from Chestnut to Walnut.

May 7 to May 14

•The contractor will perform remaining milling and overlay work on sections of route 11 Southbound from Walnut Street to Market Street. During this time, the final layer of wearing course will be placed on Front Street through the business district. The parking lines will be repainted immediately following the final paving.

• It is anticipated to complete the final wearing course on Front Street on May 13 and 14 after the festival.

• Traffic will be reduced to one lane for this work and controlled by flaggers as needed.

 

Work Area: Route 11 from Poplar Street to Arch Street

May 15 to May 31

• Complete remaining milling and overlay work on route 11 from Poplar Street (Kmart Plaza) to Auto Zone.

• Traffic will be reduced to one lane and controlled by flaggers.

Please note that in order to complete this work as fast as possible the working hours will vary from days to nights depending on the contractors’ recourses and any weather related issues.

Scroll To Top